SAP C-TS412-1909 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Reporting < 8% | Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports |
| Cost and Budgets > 12% | Describe procedures for establishing budgets and reporting costs. |
| Project Structures > 12% | Name the components of Work Breakdown Structure, Network and activities, Milestones |
| Revenues and Payments > 12% | Describe the characteristics of Revenues & Payments. |
| Dates > 12% | Describe the importance of various dates which can be tracked for projects |
NEW QUESTION 30
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.
- A. Shift activities backward or forward on the time axis where more capacities are available.
- B. Trigger automatic capacity leveling inside the project planning board.
- C. Increase the capacities of the work center in the project planning board.
- D. Maintain subordinate internal activity elements assigned to other work centers.
Answer: A,B
NEW QUESTION 31
Where do you maintain the length of the project ID?
- A. Special characters
- B. Project profile
- C. Project coding mask
- D. Project type
Answer: C
NEW QUESTION 32
To which object can you assign a factory calendar?
- A. Network header
- B. Relationship
- C. Material component
- D. Milestone
Answer: A
NEW QUESTION 33
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question
- A. Increase the capacities of the work center in the project planning board.
- B. Shift activities backward or forward on the time axis where more capacities are available
- C. Trigger automatic capacity leveling inside the project planning board
- D. Maintain subordinate internal activity elements assigned to other work centres
Answer: B,D
NEW QUESTION 34
What could be a reason to use expert mode in the valuation method for results analysis?
- A. Usage of different line ID
- B. Billing WBS elements belonging to different company codes
- C. Valuation in different currencies
- D. Assignments of different accounts for postings to financial accounting
Answer: B
NEW QUESTION 35
Which planning method can prevent further rescheduling of activities?
- A. Workforce planning
- B. Capacity levelling
- C. Partial confirmation of activities
- D. Capacity requirements activation
Answer: D
NEW QUESTION 36
What PP/DS master data is necessary for using PP/DS? Note: There are 2 correct Answers to this question.
- A. Location
- B. Material
- C. Resource
- D. Production version
Answer: A,C
NEW QUESTION 37
Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.
- A. Sales prices are maintained in the DIP profile.
- B. Usage of cost elements is mandatory.
- C. Material determination is mandatory.
- D. Sources can be based on line items.
- E. DIP is used to create a quotation.
Answer: A,D,E
NEW QUESTION 38
In your logistics project, you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?
- A. Scheduling and distribution key
- B. Capacity planner group in the network header
- C. Control key of an activity
- D. Scheduling and capacity category
Answer: C
NEW QUESTION 39
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question
- A. Standard network with activities
- B. Assignment between material and standard network
- C. A bill of material with sales views
- D. A material master with sales views
- E. A production order
Answer: A,B,D
NEW QUESTION 40
How can you confirm the working hours of different work centers for a single activity?
- A. Assign multiple work centers to the activity
- B. Enter direct activity allocation assigning multiple work centers
- C. Create multiple confirmations for the activity and use the appropriate work center for each confirmation
- D. Enter multiple work centers within a single confirmation
Answer: C
NEW QUESTION 41
Revenues & Payment
Your customer wants to plans and post revenues for WBS elements.
What is crucial for the implementation of revenues planning and posting for WBS elements?.
- A. At least one WBS element must be a billing element.
- B. Revenue planning and billing must be activated in the corresponding network type.
- C. A sales order item has to be assigned to each WBS element used for revenue planning.
- D. The indicator "Project type" must be set to "Customer project".
Answer: A
NEW QUESTION 42
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
- A. Network type
- B. Project profile
- C. Network profile
- D. Data entry profile
Answer: B
NEW QUESTION 43
Project Structure
You plan double the work on each internal activity for multiple project. What do you recommend?
- A. Double the work of each internal activity, one after another, in the project Builder.
- B. Double the capacity in the work center.
- C. Use mass change within the project Builder (CJ20N).
- D. Use mass change (CNMASS) in the project system.
Answer: D
NEW QUESTION 44
Resources
Which of the following transactions can you use to post actual cost for external processing.
Note : there are 2 correct answer for this question.
- A. Creating a service entry sheet
- B. Approval of a service entry sheet
- C. Creating a purchase order.
- D. Approval of a good receipt.
- E. Posting a goods receipt
Answer: B,E
NEW QUESTION 45
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.
- A. An activated Scheduling indicator in the control key of the internal processing activity
- B. The factory calendar in the work center used for the internal processing activity
- C. The relationships between activity elements
- D. The unit (for example, hour, day) of the field Normal Duration field of the activity
- E. Whether the work for the internal activity is greater than its duration
Answer: A,B,C
NEW QUESTION 46
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct Answers to this question.
- A. Internal orders
- B. Purchase order items
- C. Sales order items
- D. Reservations
Answer: B,D
NEW QUESTION 47
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.
- A. Goods receipt into unvaluated project stock
- B. Recording of external services in the service entry sheet
- C. Goods receipt into valuated project stock
- D. Goods receipt of a non-stock item
Answer: A,B
NEW QUESTION 48
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Structure overview for budgets
- B. Hierarchical report on budget updates
- C. Line item report for budgets
- D. Cost element report on budget updates
Answer: B
NEW QUESTION 49
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.
- A. A sales order must be created in advance.
- B. A delivery document type must be configured.
- C. A sold to party is necessary.
- D. A shipping point is necessary.
Answer: C,D
NEW QUESTION 50
You want to determine the planned costs for an internally processed activity. Which data do you need?
Note: There are 2 correct Answers to this question.
- A. Work
- B. Duration
- C. Activity type
- D. Profit center
Answer: A,C
NEW QUESTION 51
When you create a service activity in your network, what data can be entered? Note: There are 3 correct Answers to this question.
- A. Service specification
- B. Overall limit (maximum value of all unplanned services)
- C. Service purchase order number
- D. Material master within service specification
- E. Vendor
Answer: A,B,E
NEW QUESTION 52
You have saved a network and activates with assigned material components. As soon as you release the network,
you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?
- A. Missing budget for material components
- B. Missing reservations for material components
- C. Missing material availability
- D. Missing authorizations to release material components
Answer: C
NEW QUESTION 53
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?
- A. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
- B. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling
-> Purchase order monitoring -> Goods receipt -> Invoice receipt - C. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval
- D. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt
Answer: C
NEW QUESTION 54
The individual tasks in the project are mapped as activities in a WBS. Determine whether this statement is true or false.
- A. True
- B. False
Answer: B
NEW QUESTION 55
......
SAP C-TS412-1909 Exam Description:
The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.